203
FEET ABOVE THE WATER!
(Green
Bay Press Gazette, Scott Cooper Williams)
(Department
of Transportation, Jim Fowler, Frazer Chronicle)
That’s
really high, 203 feet above a river…..not nose
bleed high, but high enough that a fall would probably be your last.
The Leo Frigo Memorial Bridge has a
height of 203 feet above the Fox River on the north side of the city of Green
Bay, Wisconsin.
The
most exciting events connected with the bridge (named to honor Leo
Frigo, a civic philanthropic leader in the Green Bay area) was the occasional
suicide jumper and closings for fog, high winds, and blizzards along with ice
conditions.
I
must have driven over the structure a thousand times during my twenty five
years living in the city and I was aware of the effects of high winds…..especially
when I’d drive my tractor-trailer over the bridge. However other than the winds
or fog I never really gave traveling across the 1.51 mile a thought.
That
however all changed on September 25, 2013, on or before 4:45 A.M. when Brown
County 911 operators received multiple calls about sagging on the bridge. The
bridge was closed at 5:30 A.M. local time by local law enforcement after
investigations found a 400’ stretch of the bridge sagging approximately two
feet along the east approach of the bridge along all lanes.
Further
investigation by the Wisconsin Department of Transportation, pier number 22’s
footing was found to have settled about 2’. Initially it was not known whether
the pilings, which extend 100’ to bedrock, are still supporting the footings
under the pier.
This
double speak boils down to a very
simple fact, a concrete and steel structure, for whatever reason the support mechanism
that was supposed to keep the Frigo
bridge in an upright position…..and to not
allow any sagging activity…..failed. On October 3, 2013, initially the
Wisconsin Department of Transportation released findings of a one week
investigation that the sinking action was the result of corrosion on the
pilings, and pier number 22, the corrosion was significant enough to cause
buckling.
The
Green Bay Press Gazette stated that
the state’s highway department officials said that new testing proved that
Green Bay’s troubled Leo Frigo Memorial Bridge is on solid ground…..despite
records showing that few of the bridge’s original underground support beams
were driven down into solid bedrock.
Newly
released records of the bridge’s construction in the 1970’s, show that of the
nearly 2000 vertical steel beams, fewer than 10% were driven to the limestone bedrock
formation. In early design plans, it was recommended to drive the supports to
the bedrock formation under the bridge.
I’M
NOT AN EXPERT…..BUT
I’m
not an expert, I’ve never worked for a bridge building company, I’m not a geologist,
nor a construction engineer, but I do know how to ask questions…..and the short
research that I’ve done on this subject, (bridge building) it would seem from
what I’ve read, that the Frigo supports should have been driven to solid
bedrock.
However
officials with the Transportation Department, officials with a hell-of-a lot more
experience than I have (I have none) say that new soil borings indicate that
that the Frigo’s elaborate steel frame rests atop a hard layer of underground
earth just as stable as when the bridge opened in 1981.
Okay…..if
that was the case, how did the bridge sag by 24 inches in a day, or whatever
the time-line was, anyways, when dirt and water are mixed together…..don’t they
make mud. Are these transportation experts and officials trying to tell me that
every time I drove across that bridge, I was driving on a bridge that was
supported by mud…..possibly?
Something
doesn’t sound quite right here, and then you have the outside expert, at least
a geologist, from the University Wisconsin-Green Bay who hasn’t an ax to grind,
holds no vested interest saying that “the fact that most steel beams were not
driven down to bedrock (only about 200 of the 2000) might suggest that changing
underground soil conditions could have caused some beams to sink into the ground.
“If that happened under pier number 22, it could be happening elsewhere.” Yea
like maybe mud.
DENNIS
PAULI, JOHN LUCZAJ
Why
is there always at least two different opinions about everything, don’t these
experts ever get together, compare notes and settle on one particular answer
that everybody can accept. According to Luczaj, the geologist at the University
of Wisconsin-Green Bay maintains that investigators of the bridge have not
adequately checked all 51 piers hold up the bridge.
Luczaj
further states that the theory
reached by the investigating team is insufficient, there was very limited
science, and the geologist also said that the findings were a rush to judgment. Of the 40
beams under pier 22, state officials acknowledged that they excavated and
examined only three, partly out of concern that further investigation would
delay the bridge’s reopening to traffic.
Can’t
anybody remember the I-35W Mississippi
River Bridge disaster in August of 2007, a bridge that I crossed in my semi
at least 20 times. The bridge, built in 1965 and opened in 1967, suddenly collapsed
on August 1, 2007, and took 13 lives and injuring 145. Although the Frigo and the I-35W have only one similarity, both are bridges over a river, the
danger in under-inspection can
result in a catastrophic disaster.
Work
is scheduled to be completed sometime in January at a cost of $15 to $20
million dollars, of which the Federal Government will be picking up around 90%
of the cost. Where does the other $3 to $4 million coming from…..maybe the Army
Corp of Engineers, or the bridge construction company, and just because some
engineer say’s that the clay dirt was as firm as a rock formation, do we have
to take his word for it…..kind of like on
blind faith.
There
is a differing tone between what geologist Luczaj
says, and former state highway engineer, Dennis Pauli has to say. Pauli oversaw construction in the late 70’s
said that he is certain that
investigators have correctly identified the problem and have done an adequate job
of investigation.
Hummmmm…..let
me see, what does that word mean…..adequate….sufficient,
barely satisfactory, as much or as good as necessary, reasonably sufficient for
starting legal action. I think that the final meaning of the word “starting
legal action” might make adequate a
poor choice of words.
Luczaj
says that very little science is going into the equation of rooting out the
problem as to the reason that the Frigo sunk two feet.
Pauli
said that all the steel beams registered the required load-bearing capacity at
construction time, 150 ton each, and that he agrees that the current issue is a
combination of corrosion and buckling under pier number 22. Pauli also voiced
confidence in the state highway department’s commitment to restoring the bridge
to a safe operating condition. I can’t believe that they’d do anything half
way.
WELL
THERE YOU HAVE IT…..TWO DIFFERENT PROFESSIONALS, TWO DIFFERENT OPINIONS
You
take all the information, all the facts, put um in a big hopper and
blindly take a piece of paper with an opinion written on it. That’s no way to
come to a fact based opinion, both of these guys, Pauli and Luczaj have
undoubted knowledge and experience behind their opinion…..however…..more
questions persist, like:
a.
A preliminary design study found that limestone bedrock was located 100 to 140’
below the surface, was very competent, (strong and stable) and that the steel
frame should be driven to that rock formation…..all of the beams, why weren’t
they?
b.
Why are the records of the pile-driven work jotted down by hand in a small engineer’s log-book?
c.
Records of the 1949 beams that were driven into the earth identify only 130
reached a depth equal to where the bedrock was located?
d.
Where there vugs (small cavity or vain in rock formation) in the bedrock
formation?
e.
Why is the state transportation people worried about the time it is taking for
the repair project, shouldn’t safety be upper most in their minds…..remember I-35W!
Well
there’s my take, or rather questions with regards to the Leo Frigo Bridge and
the dipping problem it seems to have. I might be using an alternative route
even after the Frigo reopens and is deemed safe by the experts.
HAVE
A NICE DAY!
No comments:
Post a Comment